NEW RELEASE CODE SINCE Jan 2003:

1) 

CLOSED ISSUES - Since Jan 2003:

CURRENT ISSUES - Released Code:

  • BUGS:

    1. priority 1
    2. priority 2
    3. priority 3
    4. ENHANCEMENTS: (priority 4)

      • (ENHXXXX) MTA_MONITOR_EVENTS - first zoom window should be aim point.
    5. MTA Databases

      • 20 (check) speced and built being tested (phase II)
      • 10 (check) additional speced (phase III)
      • Population of pcad_qual began July 1
      • Data seeker library issues.
      • Filtering by SI - mode or at least TE/CC F/VF
    6. MTA Problem Response System:

      • System 90% obviated
      • REALTIME safe mode only
      • AP : OFF
    7. SDP

      • Eliminate N day delay before each AP run.

      OVERDUE :

      FUTURE RELEASES :

      Priorities (1-highest (up to 3) , 10-lowest (up to 30))
      
      
      
      
      1) L2 MON (MTA_SOURCE_MON)
      	Speced separately, - See XPIPE
      	Priority 5  JGP 1 Month after stable L2 source lists.
      
      
      
      2) SI-Background MTA_SIB
      	- From L2 DATA create a mask of sources
      	  +Remove these regions from the L1 data product.
      	  +create table of  /counts/time (~5 min) /energy bin
      	  +create plot of /counts/time (~5 min) /energy bin vs time
      	Purpose, track the background rate of the SIs and the sky.
      	Procedure- remove all sources from an event List.
      		Calculate /counts/time (~5 min) /energy bin
      		Energy bin and time window are parameters
      	Output: to web: tables, per OBI
      	OUTPUT to DB: RA, DEC, TIME, calculated quantities NEW DB.
      	Status :Abbey's tool almost done, no other code.
      	Priority MTA 7  RO 2 months.
      
      
      
      3) HRC/ACIS_DOSE (MTA_HRC_DOSE)
      
      	Purpose Monitor HRC dosage/pore Alert scientists if problem
      	Procedure-PerOBI make list of events/ pore pair
      		Each week create dose image/list 
      		Use (coadd/ Dmcopy )last 4 weeks to create last month
      		Use last 52 weeks to create last year 
      		Use all weeks to create mission
      	Notes: use chip coords
      	Note:  well developed may have out paced DM tools
      	Note; if cnt/pore GT Y Alert yellow, GT R RED, 
      	Note Y and R are different for the /OBI and the Weekly and the monthly etc.
      	Output Web page Hottest pores table
      	Output DB, dose list/images
      	Output  for all pore GT D, CX,CY, Total dose 
      	Status: spec 80%
      	Status tool 80%
      	Status pipeline 40% understood, not implemented 
      	Status DB 0%
      	Priority MTA 5 JGP 3 weeks
      	Priority DB 5 -AE 2 weeks	
      
      
      
      4) ACA_TRD - This is the L1 Aspect monitoring and trending. 
              Proority MTA 6 
      
      5) Monitor - DEA HOUSEKEEPING - spec delivered 3/22/99. Being handled
      through Direct DOSS tools.
      
      
      6)MTA_ACIS_CCD_MON-
      	 - From ACIS L1 Event list create
                 + Histograms
                     o pha
                     o pi
                 + Plots
                     o pha histogram
                     o pi histogram
                     o cnts vs time ( per chip )
      
      	purpose: monitor CTI, and general ACIS performance
      	procedure  OPEN ACIS L1 event lists create fixed plots and histograms
      	procedure  Open ACIS BIAS files create fixed plots 
      	output  to web pages: the plots /per obi or per bias
                    output  to DB #G64, #G2, #G8 ,#G16, Node_ID, CCD_ID. Obsid.
      	Output  to DB BIAS data: FWHM, meadn, meadian, mode, min, max,
      		node_id,ccdid, obsid.
      		THE OTHER SUMMARY INFO IN THE SPEC IS LESS IMPORTANT
      			AT THIS TIME.
      	Status: Spec 90%
      	Status: tool 90%
      	Status: Pipeline 10%
      	Status: DB 0% ; Takashi is able to use data though
      	Status; Integ Good, AP can handle this tool.
      	Priority MTA 5  JGP 2 weeks
      	Priority DB     2 AE  2 weeks
      
      
      
      
      7)Configuration tool: MTA_CHANDRA_CONFIG
      	- From RAW DATA create
      	  +tab delimited files 1 new record when each tracked value
      		changes
      	  +A plot of the spacecraft configuration vs. time
      
      	Purpose -create an easy access mission history
      	Procedure- Run ACORN TC on all dumps and associated procedures
      		developed by SJW/TI
      	Traced quantities (HRC- S HV, HRC-I HV, ACIS CR (2) ,GRAT POS
      		(4) SIM POS (2), OBSID, FMT
      	Output- to web pages:- plot of traced quantities
      	Output to DB: single file with all traced quantities throughout
      		mission (RDB and fits)
      	
      	Issue how to we manage the data product, Write the RDB to the 
      		web page and constantly replace/update FITS file.
      	
      	Status: spec 100% 
      	Status tool  100%
      	Status Pipeline  25% defined and working as cron tab
      	Status integ 50% - should be implemented as part of MTA
      		monitor_RAW?  Or as separate version of it RAWII.
      	Priority MTA 5  it works as is  RO/DP 1 month to integrate
      	Priority DB    4  ditto
              Currently handled through Direct DOSS tools.
      
      
      8)MTA_PRS  REVAMP
      	Prioity MTA 6 RO 1 Month
      
      
      
      	
      9) Integrations Tool (IT)
       	Time comps on DB items
      	I.e. RPMs * time = rotations.
      	Status undone I think this is a pure DB app,   DB priority 6.
      
      
      
      
      
      
      
      
      
      
      

      Lower priority

      1. FLAG - still unstable, these need to be fixed (Priority 7)
      2. Processing speed. (priority 9)
      3. Bias_Mon (priority 7)
      4. Check_ACIS LOAD (priority 7) spec delivered to ISOBE, Shanil will develop.
      5. ACIS configuration (priority 7) ibid
      6. Merged Status files. (priority 7)
      7. Determine pointing offsets - DOSS direct development underway.
      8. MTA DI - string handling. - PSUEDO code exists (Priority 7)
      9. Trend HRMA focus (this covers 10 MTA tasks & gets complicated) (priority 7) -Scheduled for DOSS development June 2000.
      10. SIM positional accuracy tool (includes repeatability, settling time and hysteresis.) This is being handled in by DOSS direct right now (priority 8)

    December 2000

    1. Other issues - Highest priority -9
    2. ACIS trending
    3. HRC trending
    4. PCAD trending
    5. Other issues - Lower priority -10
      • Counting tools
      • Detect flickering pixels on ACIS
      • Monitor CCD/HRC/SIM tilts (Part of ACA Mon)
      • Determine grating orientation (Part of grate_mon)
      • Dump and compare is on indefinite hold.